Final Mile

Bus stop sign mounted on a pole with people waiting for the bus in the background

  • Project Stage: Completed
  • Construction End : September 2024
  • Intent:To reduce the barriers that may prevent residents, workers, and visitors from using alternative modes of transportation.  Installed at high-use bus stops and parks:
    • 62 Bus stop information holders
    • 43 Solar-powered transit flagging devices / lights
    • 121 Bicycle racks (parking 242 bikes)
    • 60 Trash / recycling receptacles
    • 28 Secure bicycle lockers (securing 56 bikes and accessories)
    • 17 Bicycle repair stands (Fixits & pumps)
  • Project Updates:
    • Map of bicycle facilities: (link)
    • Remaining features: trash receptacles, signs, and flagging stations to be installed 2024
    • Grant supplemental agreement, January 2024 (link)
    • All bicycle racks, repair stations, and lockers have been installed as of October, 2023
    • Construction bid award, November 2022: (link)