South Street

A group of workers pouring and finishing concrete

  • Project Stage: Completed
  • Construction Start: May 2024
  • Construction End Estimate: Spring 2025

  • Intent: Complete Streets improvements to South Street includes paving, Americans with Disabilities Act (ADA) sidewalks, curb ramps and pavement markings, bike lane facilities, and landscaping from Duval Street to Reynolds Street.

  • Project Updates:

    • Demolition start along South St: June 10, 2024

    • Demolition start along Reynolds St: May 28, 2024

    • Tree Commission Meeting: May 7, 2024 (link)

    • Construction bid award, March 2024 (link) For your convenience, the legislation link provides the project plans below:

      • Roadway and drainage plan (link)

      • Striping and signage plan (link)

    • Design task order, November 2022 (link)